In 2017 DMCA Architects started working on a challenging scheme to add a roof terrace to a Grade II listed Georgian property in Southwark. The four-storey building contained two flats, both owned by the client: the upstairs flat had no external amenity space, while the basement flat had only a 6m² patio which was overshadowed by neighbouring buildings. 
Securing permission for rooftop outdoor space required lengthy negotiations with the planning authority because of the building's Grade II listing. Following initial pre-application consultation, the conservation officer guided us towards an independent terrace deck above the existing butterfly roof, retaining the entire structure of the existing roof below. This approach secured Listed Building Consent in May 2018, but offered very limited terrace area and made it almost impossible to achieve terrace access that complied with Building Regulations.
Further investigation established that the roof structure had been heavily altered and was not original, although its form broadly matched the assumed profile of the original house. Our analysis of the complete terrace demonstrated that the tapered plan and a unique central staircase distinguished this end-of-terrace property from its neighbours. These differences raised questions about whether the butterfly roof form was original. On this basis, we prepared a new application to replace the existing butterfly roof with a new flat roof  structure and access via a glazed, motorized hatch. To meet the local authority's requirement to maintain some of the original pitched slate roof character, the revised design replicated a narrow section of pitched roof on each side of the access hatch. After further negotiation, this application was granted Listed Building Consent in August 2020. 
The approved design creates a larger flat roof area with a front terrace and a slightly smaller rear terrace. A raised section between them accommodates a zinc-clad motorised access hatch and this raised section also projects above a new bathroom on the half-landing receiving daylight through an obscure-glazed walk-on rooflight. Listed Building Consent and Planning Permission were eventually granted for this final scheme. Work began in July 2023 with alterations to the staircase and construction of a new first-floor bathroom. Terrace works have yet to begin but they are expected to proceed when funding permits. 
Context Amenity Study
Context Amenity Study
Sightlines
Sightlines
Access Hatch Details
Access Hatch Details
Bespoke Staircase Details
Bespoke Staircase Details
Section Through Terrace
Section Through Terrace
Project Information:
Date: 2017- (TBC) | Contract Value: Approx. £175,000 (2022) | Contract: TBC | Contractor: TBC 
Structural Engineer: SD Structures | Heritage Consultant: Keystone Heritage (Planning & Heritage Consultancy) | Party Walls: Osprey Building Consulting